HongKong 3RS 3206-Contract For Land DCM Works

Summary

Reclamation work to expand the third runway of Hong Kong International Airport located in LANTAU. The first ground improvement was completed through the marine DCM method, and the second ground improvement was carried out by applying the land DCM method at the same time as sand reclamation. In particular, the airport's altitude restricted area during the relevant construction section is applied with our new lot technology The ground has been improved.

  • Begin 2019.12

    Client AAHK

  • Location Tung Chung, HongKong

    Explanation Ground improvement / DCM improvement : 1,439,174㎥ (17,818)
    Stratum : Reclaimed soil / MD / Alluvium